Tough Driving Conditions At Grand Calumet River Remediation |
Sometimes projects turn out to be easier than expected, but La Crosse, Wisconsin-based J.F. Brennan Company, Inc. knows you
can't count on that. That's why the experienced piling and dredging specialist tries to anticipate the unanticipated. Such was
the case at the Grand Calumet River remediation project in Gary, Indiana, where J. F. Brennan was hired to dredge nearly six
miles of the river.
J.F. Brennan was the dredging subcontractor to Earth Tech, who was employed by U.S. Steel - a company that had been working
with the EPA on the Grand Calumet River project since the early 90's. J.F. Brennan's portion of the project involved removal
of impacted sediment, thereby widening and deepening the channel in a portion of the river that had been closed by silt.
 |
|
Gary Dondlinger and Rodger Bean of J.F. Brennan Company, Inc.
|
"This was a very complex project," commented Anthony Binsfeld, president of J.F. Brennan. "It is the largest environmental
remediation project ever done with hydraulic dredging in the western hemisphere."
The Grand Calumet River project had three phases. First was the construction of a CAMU (Contained Active Management Unit),
a structure into which the dredged spoils are placed. The second phase entailed construction of a project-specific water
treatment plant - a system designed to clarify return water before discharging it into the river. The final phase was the
hydraulic dredging. That involved the removal of more than 700,000 cubic yards of impacted sediment and placing it into the
CAMU, a permanent holding area that will be capped once the material has been dewatered.
During the course of project planning, the project team engaged in some "what if" contingency planning. That led to a review
of bank stability because of the proximity of a U.S. Steel coke plant that had been located on the river for over 100 years.
"From the review we concluded that, after dredging, there was a bank failure likelihood," Binsfeld recalled. To prevent the
bank from caving in and disrupting plant operations, the riverbank had to be stabilized before dredging could begin.
Consulting engineers conducted a slope stability investigation and recommended installation of steel sheet piling.
Due to the hard driving soil conditions, J. F. Brennan found it difficult to install piles to the required depth. "From
borings that gave us blow counts in excess of 100-blows/ft., we knew the job was going to be difficult," Binsfeld remarked.
"We had a list of methods to use and tried several drivers."
Initially, J.F. Brennan tried a mid-sized vibratory driver with mixed success. Some sheets could be driven to grade, but
not at the desired production rate. Next they tried impact hammers, but found they were causing excessive damage to the
pile tops. Finally, Binsfeld turned to Hammer & Steel for help. "I've worked with Joe Dittmeier for many years," he
explained. "Hammer & Steel helped us find the best equipment for the job."
The advantage that a company like Hammer & Steel offers in a situation like this is that they have such a large range
of equipment available. "Some of our competitors represent only one manufacturer," explained Hammer & Steel's regional
manager, Mike Ormsby. "We've gone out and sought the best products within a number of different categories from a number
of different manufacturers," he said. With such diverse product offerings, Hammer & Steel has a unique ability to solve
a wide range of problems.
"When J. F. Brennan came to us, they had already tried several methods," Ormsby recalled. Since they needed to pick up
production, Hammer & Steel suggested trying two PVE Model 52M vibratory drivers-equipment much larger than normally
required for the 40' piling sections. They worked very well.
"These PVE systems are an extremely high quality tool, able to drive piling in the toughest driving conditions,"
commented Ormsby. The 52M-system features 4500 in. lb. eccentric moment, a 750 HP power unit, and forced lubrication
of the exciter gearbox.
The pile driving work began in November 2002 and was completed in March 2003. The units performed trouble-free. The
unique warm-up features came in handy during the cold months of January and February 2003. Approximately 3,000 wall
feet of JZ-120 heavy cold-formed piling was installed.
"Even with the PVE units, it was still tough driving," said Binsfeld, "but they worked well. It was a challenging project,
as we knew it would be. We relied on Hammer & Steel to help out, and they came through for us."
|
| |
| |
|
 |
|
 |
| Company Headquarters |
Branch Offices |
11916 Missouri Bottom Rd.
St. Louis, MO 63042
Ph: 800.325.PILE (7453)
Ph: 314.895.4600
Fx: 314.895.4070 |
Benicia, California
Ph: 877.224.3356
Boston, Massachusetts
Ph: 508-888-3314
|
Green Cove Spring, Florida
Ph: 904.284.6800
Houston, Texas
Ph: 281.852.1136
|
Kansas City, Kansas
Ph: 913.681.9295
Vancouver, Washington
Ph: 425.296.4518 |
Minneapolis,
Minnesota
Ph: 952.469.6060
|
|
|
|